The Manager Lane
  • Home
  • About
  • Contact
  • Resources
  • Tools
No Result
View All Result
  • Home
  • About
  • Contact
  • Resources
  • Tools
No Result
View All Result
The Manager Lane
No Result
View All Result

The Ultimate Guide to Creating an MS Project Schedule & Keeping on Track

Emad by Emad
June 11, 2023
A A
Home Project Management
3.1k
VIEWS
ShareShareTweet

In the planning fundamentals article, we discussed the main concepts of project planning and scheduling. In this tutorial, I’ll go through a demo project to practically show you how to apply these concepts to create a project schedule using MS Project.

The reason for choosing MS Project is it is one of the most common scheduling tools on the market. This is not to say it is the only tool out there. However, if you know how to use it, you can easily use any other planning and scheduling software.

Table Of Contents
  1. Step 1: Define the Project Scope
  2. Step 2: Create the Work Breakdown Structure (WBS)
  3. Step 3: Identify the Project Tasks
  4. Step 4: Estimate the Duration of Each Task
  5. Step 5: Identify the Dependencies Between Tasks
  6. Step 6: Create a Project Schedule
  7. Step 7: Improve the Schedule Visualization
  8. Conclusion:

Step 1: Define the Project Scope

In this example, I will assume the project scope is the design and construction, including the supply of manpower, tools, materials, and equipment to build a new warehouse.

That statement above is an introductory scope statement, but as explained previously, the scope definition can be covered by many different documents, including:

  • Drawings
  • Specifications
  • Deliverables List
  • Scope inclusions 
  • Scope exclusions

Step 2: Create the Work Breakdown Structure (WBS)

In this step, we need to break the scope into discrete scope elements that can be used to control the schedule and cost. Each of these elements, or WBS, can include several activities. 

In our example, the WBS would be the site investigation, design development and construction. The reason I choose this WBS is because each of its elements represents a discrete scope. In the same example, we can also include procurement or final testing of the facility.

Note: The full project scope must be represented in the WBS. Ask yourself if a scope element can’t be covered in one of these WBS, then think of creating a new WBS to include it.

Tip: Try this AI-powered tool to generate the WBS.

Step 3: Identify the Project Tasks

As we developed the project WBS, we needed to start generating the activities within each. For example, the site investigation WBS includes the site survey, geotech study and service location.

There is no limit on the number of activities that can be developed or the level of detail to add to each WBS, but as a rule of thumb, they should be proportional to the project duration and complexity.

The project managers can decide on the level of detail that helps them manage the project schedule.

Project WBS and Activities

Project WBS and Activities 

Note: Please note the numbering system of the WBS. i,e: 1, 1.1, 1.2, etc.

To implement the same WBS in MS Project, you start by navigating Gantt Chart Format and then selecting Outline Numbers.

Gantt Chart select
Outline Number select

Start typing the WBS elements and activities in the Task Name window. 

MS Project will automatically create a new WBS for each entry. 

To change a WBS into an activity, select the activity, then click the Intent Task.

Intent Task

This is what the schedule looks like when all activities are entered:

Activity List

Step 4: Estimate the Duration of Each Task

Now that we have the skeleton of the schedule, the next step is to estimate each activity’s duration. Please refer to this section from the planning article, where I explain the different methods of estimating the activity duration.

In our example, we assume the activity durations are resource-driven, hence are calculated based on the quantity, production rate and number of resources.

For instance, if the activity (1.2 Geotech Study) requires the drilling of 20 boreholes and the team only has one drilling rig that drills four bores/day, then the duration of this activity is (20 / 4) = 5 days. 

We can apply the same concept to all other activities. 

This is what the schedule looks like when the activity duration is estimated:

Activity Duration

Step 5: Identify the Dependencies Between Tasks

In the planning article, we discussed the different types of activity relationships, including Finish-to-Start (FS) being the most common.

For our example, the planning logic is that the site investigation must be finished before the design can start; consequently, the design must be finished before construction can start.

A negative or positive lag can be introduced in the activity relation to show an overlap or a gap between the activities.

The idea is that project managers apply logic based on how they foresee the project being executed.

To implement these relations in MS Project, there are two methods:

Method one: select all (FS) activities using Ctrl and left-click, then click on the link icon Link Icon

Link Icon 2

Method two: right click on an activity, select information, select Predecessors, then enter the activity ID you want to link to, and then click Ok.

Please note the activity ID is the serial number of activities and not the WBS.

Note: you can use the Lag field to enter the lag days between the two activities.

If you use method two, you must do this for each activity.

Activity Link
Linked Schedule

Step 6: Create a Project Schedule

The most common method of creating the project schedule is called the Critical Path Method (CPM), which identifies and calculates the critical activities on the schedule. The remaining activities are considered non-critical.

To recap these definitions:

  • Critical activities: are activities that have no float or slack, which means any delay to them would cause a delay to the schedule’s completion date.
  • Non-Critical activities: are activities that have float or slack, which means they could be delayed for a specific duration without causing a delay to the overall completion date.

To use the CPM in MS Project, choose Gantt Chart Format, then select Critical Tasks.

Critical Tasks

The standard setting is the non-critical activities are shown with a blue colour, whereas the critical activities are shown with a red colour, but this can be changed. 

See the screenshot below of the schedule. You will notice because all the activities are FS, all activities on this schedule are critical:

Linked Schedule Critical

Step 7: Improve the Schedule Visualization

The final step in creating the schedule is to ensure the visualization is easy to follow.

This can be based on personal preference; however, by tweaking the appearance of the Gantt chart, you can use it predominantly to review and track the schedule.

Tip #1: Remove the relationship arrows between the activities. This might seem counterintuitive, but it is not, as you can still follow the relationship by looking at the Gantt chart or using the predecessor column in the main schedule.

To do this, Right click on the Gantt Chart area, select Layout, and then check the first box.

Link Arrow

Tip #2: Add the activity name to the activity bar. To do this, right-click on the Gantt Chart area, select Bar Styles, select Critical from the Text box, select Right and choose Name from the drop-down menu.

Bar Style

Tip #3: Adjust the timeline to suit the schedule duration. To do this, right-click on the Gantt Chart top calendar section, click on Zoom, then Select Entire Project, or Select Custom and enter the total duration that you want to be shown in Gantt Chart.

This is what the final schedule looks like.

Final Schedule

Conclusion:

By following the step-by-step process for creating a project schedule and incorporating the visualization tips mentioned above, you can produce a functional schedule that your project team can effectively use to plan and monitor the project’s progress.

Tags: MS ProjectProject Management SoftwareProject Planningproject scheduling
Previous Post

The Top 10 Project Management Mistakes to Avoid

Next Post

How to CONTROL Scope Creep In Your Next Project?

Emad

Emad

With two decades of experience managing intricate and demanding projects, my goal is to impart my expertise and insights to fellow project managers, assisting them in achieving successful delivery outcomes.

Related Articles

Earned Value Management
Project Management

Earned Value Management: Simplified!

March 2, 2024
AI in Project Management
Project Management

Four Ways AI Can Supercharge Your Project Management Today!

February 20, 2024
Project Management Acronyms
Project Management

Project Management Acronyms: Your Time-Saving List

December 30, 2023
Trello Screenshots
Project Management

Project Manager Salary: Unlocking Your Earning Potential

December 25, 2023
Project Management Books
Project Management

The 7 Best Project Management Books

December 6, 2023
Project Manager
Project Management

Unpacking Project Manager Careers: Your Questions Answered

November 11, 2023
Next Post
Project Scope Creep

How to CONTROL Scope Creep In Your Next Project?

Popular Articles

  • MS Project Schedule

    The Ultimate Guide to Creating an MS Project Schedule & Keeping on Track

    0 shares
    Share 0 Tweet 0
  • Project Management Acronyms: Your Time-Saving List

    0 shares
    Share 0 Tweet 0
  • Hive Project Management: The Ultimate Guide

    0 shares
    Share 0 Tweet 0
  • Google Project Management Certificate: Is It Worth It?

    0 shares
    Share 0 Tweet 0
  • The 7 Most Important Interpersonal Skills for Project Managers

    0 shares
    Share 0 Tweet 0

Categories

Tags

AI tools (1) Business (2) Career Development (3) Leadership (1) MS Project (1) Personal Development (1) Project Budget (1) Project Budget Contingency (1) Project Change Management (1) Project Contingency (1) Project Cost Management (3) Project Management (22) Project Management Acronyms (1) Project Management Books (1) Project Management Courses (1) Project Management Knowledge (14) Project Management Methodologies (1) Project Management Software (6) Project Management Template (1) Project Manager (5) Project Manager Career (3) Project Manager Salary (1) Project Planning (3) Project Risk Management (1) project scheduling (1) Project Time Management (1) Scope Creep Management (1) Scope Management (2) Stakeholder Management (1)

Get the latest posts notification. No email required.

SUBSCRIBE
  • The Manager Lane
  • About
  • Contact
  • Resources
  • Tools
  • Privacy Policy
© 2022 The Manager Lane

Welcome Back!

OR

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Home
  • About
  • Contact
  • Resources
  • Tools